Sewerage
Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Pump Stations, STP and Sewer network work ongoing.

45% Completed

Water
Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Water & Sewerage
Ongoing

PS & Sewer network work ongoing.

57% Completed

Ongoing

EMD works ongoing.

75% Completed

Completed [2023]

Water and Sewerage Networks are successfully completed.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

EMD works & Tank installation work ongoing.

80% Completed

Ongoing

PS, STP & Sewer network work on progress.

42% Completed

Ongoing

Electro mechanical design works and sea outfall works ongoing.

72% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Electro mechanical design works & Tank installation work ongoing.

67% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

PS, Sewer network & meter installation work on progress.

47% Completed

Ongoing

PS,STP & Sewer network work ongoing.

44% Completed

Ongoing

EMD works ongoing.

75% Completed

Completed [2023]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

Electro mechanical design works & Tank installation work ongoing.

65% Completed

Ongoing

Sewer component testing & commissioning Successfully completed.

45% Completed

Ongoing

Electro mechanical design works and sea outfall works are ongoing.

93% Completed

Ongoing

Electro mechanical design works and sea outfall works are ongoing.

73% Completed

Completed [2022]

Successfully completed the testing & commissioning.

100% Completed

Ongoing

EMD works & Tank installation works are ongoing.

74% Completed